Fence Installation Scope of Work Template (Free Example)

Fence jobs create arguments about the property line, rocky ground and a gate that was never in the quote. A written scope fixes the length, height, material and gate count before the first post goes in.

Quick answer

Who is responsible for the property line?

The property owner. Your scope should say the client points out the line, and that you build where they mark it.

Skip the copy and paste.

Type your messy notes and ScopeFast writes a scope like this one for your project, checks it for risky wording and gives you a ready-to-sign PDF. Your first one is free.

Make my fence installation scope free →

Example: fence installation scope of work

Scope of work

Install 150 feet of 6-foot wood privacy fence with one gate

What's included

  • ✓Set the fence line from the stakes or survey the client provides
  • ✓Dig post holes and set posts in concrete
  • ✓6-foot cedar privacy panels along 150 feet
  • ✓One 4-foot walk gate with latch and hinges
  • ✓Haul away extra dirt and debris
  • ✓Final walkthrough with the client

What's not included

  • ✕Property survey or any boundary disputes with neighbors
  • ✕Removing an old fence (quoted separately)
  • ✕Permit fees and HOA approval
  • ✕Staining or sealing the wood
  • ✕Extra digging cost for rock or heavy roots (quoted when found)

Revisions

None. The layout and gate position are agreed on a marked-out plan before digging starts.

Timeline

3 to 4 days on site, starting about 3 weeks after the deposit, weather permitting.

Fee and payment

$6,300 total. 40% ($2,520) to order materials, 60% ($3,780) on completion.

Changes and extra work

Added length, extra gates or a changed layout are priced in writing before work continues.

Approval

Client signature: ____________________   Date: __________

Tips for fence contractors

Questions

Should the scope mention weather delays?

Yes. One sentence saying dates move for rain or ground conditions avoids arguments about late starts.

Scope creep stops here.

Turn your notes into a professional scope of work in 30 seconds.

Create my free scope →

Get new templates and guides by email

Leave your email and we will send you new scope of work templates and short tips for stopping scope creep. No spam. Reply to any email to unsubscribe.

Client asked for something extra?

Put it in writing before you start. Use a free change order template so extra work gets approved and paid.