Flooring Installation Scope of Work Template (Free Example)

Flooring jobs go sideways at the subfloor. Once the old floor is up, damage or moisture shows and the price changes. A written scope sets the area, the material and what happens when the subfloor needs work.

Quick answer

How much extra flooring should the scope include for cuts?

Many installers order about 5 to 10 percent extra for cuts and waste. Write the percentage in the scope so the material quantity is not a surprise.

Skip the copy and paste.

Type your messy notes and ScopeFast writes a scope like this one for your project, checks it for risky wording and gives you a ready-to-sign PDF. Your first one is free.

Make my flooring installation scope free →

Example: flooring installation scope of work

Scope of work

Install luxury vinyl plank flooring in a 600 sq ft living area and hallway

What's included

  • ✓Remove old carpet and pad, and haul away the debris
  • ✓Check the subfloor and level minor dips up to 1/8 inch
  • ✓Install luxury vinyl plank in the chosen style, with about 5% extra for cuts
  • ✓New transition strips at doorways
  • ✓Install shoe molding along the baseboards
  • ✓Final sweep and walkthrough with the client

What's not included

  • ✕Moving furniture (the client clears the rooms before the start date)
  • ✕Repairing damaged subfloor or moisture problems
  • ✕Replacing baseboards or trim
  • ✕Flooring cost above the agreed material allowance
  • ✕Stairs and any rooms not listed

Revisions

No design revisions. The plank color and style are signed off on a sample before materials are ordered.

Timeline

2 to 3 days on site after materials arrive, usually within 2 weeks of the deposit.

Fee and payment

$4,200 total for materials and labor. 50% ($2,100) to order materials, 50% ($2,100) on completion.

Changes and extra work

Subfloor repairs or extra rooms are quoted in writing before work starts.

Approval

Client signature: ____________________   Date: __________

Tips for flooring installers

Questions

What if the subfloor has damage?

List subfloor repair as not included, and say it will be quoted once the old floor is up and the damage can be seen.

Scope creep stops here.

Turn your notes into a professional scope of work in 30 seconds.

Create my free scope →

Get new templates and guides by email

Leave your email and we will send you new scope of work templates and short tips for stopping scope creep. No spam. Reply to any email to unsubscribe.

Client asked for something extra?

Put it in writing before you start. Use a free change order template so extra work gets approved and paid.